If you cross the Boardman River near , your route is back. The Grand Traverse County Road Commission announced Wednesday that the Beitner Road bridge reopened to traffic at 3 p.m., the first time vehicles could cross there since mid-April. The bridge is rebuilt and open just seven months after it washed away.

The rebuild by the numbers

$3.7 million
for the rebuild, done by Anlaan Corporation
7.8 feet
the Boardman River hit at Beitner Road on April 14

Source: mlive

Historic flooding in April collapsed the bridge, and the washout lengthened commutes on a key east-west corridor that drivers use to avoid heavier traffic. Reconstruction began in August with a goal of reopening by the end of the year. In October, Dan Watkins, managing director of the road commission, said it would open "sometime in November." Sometime turned out to be Nov. 18.

  • Failure: early April 15, after rain and snowmelt
  • Original plan: construction in early 2027
  • More on road projects: gtcrc.org

The crossing was out from April to November, with rebuilding since August

April to November 2026

AprAMayMJuneJJulyJAugASeptSOctONovN
Bridge closedBeitner Road
ReconstructionBeitner Road

2 at once, Aug.–Nov.

Sources: mlive, WPBN

View as table
ProjectWhereWhen
Bridge closedBeitner RoadApril to November 2026
ReconstructionBeitner RoadAugust to November 2026

Sources: mlive, WPBN

Read it in the full edition

More from Friday’s edition

Read the edition
All getting around news
  1. 9and10News.comNov. 19

    Downtown Traverse City Light Parade will bring road closures this Saturday, on 9and10News.com

    The Downtown Traverse City Light Parade will take place this Saturday, Nov. 21, bringing illuminated floats and road closures to the downtown corridor.

  2. The TickerNov. 19

    TVC Board Approves Raises, Bonuses, on The Ticker

    Employee raises for Cherry Capital Airport employees for 2027 and bonuses for this year were approved this week by the Northwest Regional Airport Authority Board. The airport board (pictured above) approved several wage and salary increases for Cherry Capital Airport’s management, operations, maintenance and other staff recommended by the board’s Personnel Committee after its meeting …